A commercial fire risk assessment is a structured review of your property that identifies what could start a fire, who would be harmed, and whether the fire protection equipment on site will work when it is needed. The paper review is only half of it. The other half is a physical look at the hydrants, sprinklers, standpipes and backflow assemblies that the assessment relies on, and that is where we start at FourPoint Fire & Water. Our services include inspection, installation, maintenance, design and consulting for fire hydrants, sprinkler systems, standpipes, backflow prevention, cross-connection control and related underground piping, serving Grande Prairie, Dawson Creek and the Peace Region.
TL;DR
- A fire risk assessment identifies hazards, identifies people at risk, evaluates and reduces the risk, records the findings and plan, and is reviewed on a schedule and after changes.
- In Alberta the owner or the owner’s agent is responsible for meeting the National Fire Code, Alberta Edition, and for keeping inspection, testing and maintenance records on site.
- Hydrants, sprinklers and standpipes are part of the assessment: their condition, access and records show whether the plan on paper matches the property.
- Review the assessment at least once a year and after any change of use, storage, layout or equipment, or after a fire or near miss.
- Contact us to confirm availability for your location. We offer 24 hour emergency response for locations within 200 km.
Table of Contents
- What a commercial fire risk assessment is
- The five steps, applied to a Canadian commercial property
- What a site survey adds to the paper assessment
- Why hydrants belong in the assessment
- Sprinklers, standpipes and backflow in the same review
- Records: what Alberta owners keep on site
- How often to review
- Who does the work, and what to ask for
- Perspective
- Getting help for your property
- FAQ
- Sources
What a commercial fire risk assessment is
The term is used loosely, so it helps to separate three things that are often confused.
| Activity | Who carries it out | What it produces |
|---|---|---|
| Fire risk assessment | The owner, manager or an agent they appoint | A written review of hazards, people at risk, controls and actions |
| Site survey or technical site assessment | A fire protection contractor | An inventory of systems and equipment, their condition and their maintenance needs |
| Fire safety inspection | The authority having jurisdiction, such as the fire department | An enforcement finding against the fire code |
British Columbia draws the line clearly: its Office of the Fire Commissioner describes a fire safety assessment as a process the owner or authorized agent uses to monitor compliance with the BC Fire Code, while only a designated fire inspector may conduct a fire safety inspection. Alberta uses different wording, but the principle is the same: the owner does the self-check, and the authority inspects.
The UK government’s guidance gives a useful definition of the idea itself: an organised, methodical look at premises and activities to judge how likely a fire is to start and cause harm. It also separates a hazard (anything that could cause harm) from a risk (the chance that the harm occurs). A pallet of packaging is a hazard. A pallet stacked against a heater in a corridor that staff use is a risk.
The five steps, applied to a Canadian commercial property
The five-step method comes from the UK government, which sets out the same sequence used by most assessment templates. Canadian codes do not prescribe these exact steps, but the sequence works as a practical frame and every step maps onto an Alberta requirement.

Step 1: Identify fire hazards
Walk the property with a floor plan and list ignition sources, fuel and oxygen sources. The UK checklist names electrical equipment, smoking, arson, heating, cooking, housekeeping, contractors and hot work such as welding and grinding. In older commercial buildings, outdated wiring is a common source, and an electrical compliance inspection with a detailed report is one way to document the condition of the electrical system before you rate that hazard.
For an industrial site, add dust, flammable and combustible liquids, and any process that produces heat. For a multi-tenant building, add what each tenant stores and does, since their activities change your risk.
Step 2: Identify people at risk
List who is in the building, when and how well they can leave. The same checklist points to night staff, visitors, children, older people, disabled people and lone workers. A warehouse with one person on the night shift and a yard 200 metres from the nearest door has a different evacuation problem than a daytime office.
Step 3: Evaluate, remove or reduce the risk
This step covers escape routes, alarms, exit signs, emergency lighting, extinguishers and the separation of ignition sources from fuel. It is also where fixed fire protection belongs: sprinklers that control a fire early, standpipes that give the fire department hose connections inside the building, and hydrants that supply water outside. Evaluating them means asking whether each one is present, accessible, tested on schedule and free of known deficiencies.
Step 4: Record, plan and train
Write down the findings, the actions and the emergency plan. In Alberta this connects to the fire safety plan, which CCOHS describes as a detailed document for a specific building or property covering evacuation, maintenance and housekeeping, and ways to limit fire damage. We cover the content in our guide to a fire safety plan for commercial buildings in Alberta.
Step 5: Review and update
The review is covered in its own section below, because the triggers matter as much as the calendar.
What a site survey adds to the paper assessment
An assessment completed at a desk records what you believe is installed. A technical site survey records what is actually there. CCOHS recommends that the audit behind a fire safety plan cover site layout, entry and exit points, roadways, building use, storage, water or fire department connections, alarm systems and sprinkler systems, and that the plan include diagrams of each system’s type, location and operation.
A survey of the fire protection side typically produces:
- An equipment list: every hydrant, sprinkler riser, standpipe, fire department connection and backflow assembly, with location and size.
- The condition of each item, for example port caps, valves, signage and clearances.
- Gaps in access, such as blocked fire lanes or obstructed connections.
- A list of the test and maintenance tasks each system needs and when they fall due.
- Missing or outdated records.
This is the kind of technical site assessment and equipment identification we carry out, with the operating context of the property in view before any work is arranged. Many properties do not have a complete picture of their private hydrants and underground piping, and the survey fills that in.
Why hydrants belong in the assessment
Hydrants are easy to overlook because they sit outside, but they are the water supply the fire department depends on at your address. A private hydrant on a commercial or industrial site is normally the owner’s responsibility to maintain, and an assessment that ignores it leaves the exterior water supply unexamined.
What the code and municipal guidance look at is concrete. The City of London, Ontario, citing the Ontario Fire Code in its fire safety plan template, requires hydrants to be inspected annually and after each use, with port caps secured wrench-tight and removed annually to check connections for wear, rust or obstructions, barrels checked for accumulated water, and the main valve operated fully each year. That is Ontario’s rule, but it shows what a competent hydrant inspection involves. In Alberta, Edmonton’s business checklist requires at least one metre of clearance on all sides of each hydrant, a no-parking area, and clear fire-department access lanes.

In the Peace Region, winter adds a second set of questions. A hydrant barrel that holds water can freeze, and snow storage can bury a hydrant or block a fire lane. Our hydrant work includes inspection, preventative maintenance, repair, replacement, installation, troubleshooting, excavation and underground hydrant repairs, along with work on frozen hydrants and winter-related failures. Each finding in your assessment about a hydrant can be matched to one of those tasks.
What to record for each hydrant
- Location, ownership (private or municipal) and a number or label.
- Visibility and clearance, including snow and vehicle parking.
- Condition of caps, threads, barrel and operating nut.
- Date of the last inspection and flow check, and who performed it.
- Any open deficiency and the date it was corrected.
For properties with several private hydrants, private hydrant inspection and maintenance on a set schedule keeps those entries current. Municipalities that manage a public network can look at municipal hydrant maintenance programs.
Sprinklers, standpipes and backflow in the same review
Water-based systems are held to a recognised standard. The Town of Morinville’s building owner guide states that under Division B Article 6.4.1.1 of the Alberta fire code, water-based systems must be inspected, tested and maintained in conformance with NFPA 25-2017, and that in most cases only qualified personnel acceptable to the authority having jurisdiction may do the work. NFPA 25 is the standard for inspection, testing and maintenance of water-based fire protection systems.
The frequencies you will see in municipal templates include weekly checks of water supply pressure and sealed-open valves, monthly alarm testing, and annual checks of hangers, sprinkler heads and flow alarms. The London template lists these by Ontario Fire Code article; the Alberta version follows NFPA 25 and your local authority. Our sprinkler inspections and sprinkler repairs cover that work, and we also handle standpipe systems, backflow prevention testing and cross-connection control. Backflow assemblies matter to the assessment because they protect the potable water supply from contamination through the fire line. Our guide on fire backflow testing for property managers explains the schedule.
Impairments belong in the plan too. When a sprinkler or alarm system is out of service, the London template calls for service to remaining portions to be maintained, a fire watch where necessary, and written notice to the fire department for shutdowns longer than 24 hours. Decide in advance who makes those calls.
Records: what Alberta owners keep on site
An assessment is only as good as the evidence behind it. The City of Calgary’s guidance, based on the National Fire Code 2023 Alberta Edition, requires on-site retention of initial verification reports for the life of each system, the current and previous five years of test, inspection and maintenance records, drill and evacuation records, and an annually reviewed fire safety plan. Proof that a deficiency was resolved is kept with the original deficiency report. Calgary also asks for a printed binder labelled Life Safety Records, kept in the fire safety plan box near the main entrance, the alarm and control room, or a central records room.
Morinville’s older 2019 guide states that records must be kept at the premises, that at least the current and previous year’s records must be available, and that no record may be destroyed within two years of being prepared. Because municipalities set their own expectations, confirm the retention period with your local fire department. Our summary of what Alberta building owners must maintain under the fire code lays out the owner’s side in plain terms.
When a defect is found, the Morinville guide says the owner or authorized agent must take corrective action immediately, or it may be treated as a violation of the Alberta Safety Codes Act. Build that into your action list: each finding gets an owner, a date and a closing record.
How often to review
The UK fire service guidance from Devon and Somerset recommends reviewing the assessment at least annually and after significant change: a change of use, new storage of chemicals or dangerous substances, large changes in stock, a building alteration, or a fire or near miss. That is a sound working rule for any Canadian commercial property.
British Columbia gives a risk-based pattern for authorities’ inspection frequency: every three years for low-risk buildings, every two years for medium risk and annually for high risk, adjusted as factors such as age, maintenance history and occupant behaviour change. It describes inspections by the monitoring entity, not your own review cycle, but it shows the logic: the higher the risk, the shorter the interval.
For a property manager, a practical calendar looks like this:
- Annual full review of the assessment and fire safety plan.
- Review of hydrant, sprinkler, standpipe and backflow records when each scheduled test falls due.
- A fresh review after a tenant change, renovation, new storage, a fire system impairment or an incident.
- A walk of hydrants and fire lanes after the first heavy snowfall and again after spring thaw in the Peace Region.
Who does the work, and what to ask for
You can complete the assessment in-house if someone on your team knows the building and the code. The fire protection findings are different: water-based systems should be serviced by qualified personnel acceptable to the authority having jurisdiction, as the Morinville guide says. Our services are led by Kevin Ballantyne, a Red Seal Journeyman Sprinkler Fitter who entered the trade in 2001 and earned his journeyman ticket in 2014.
When you commission a survey or service, ask that the scope, the site context and the equipment details are settled before work is arranged, and that the deliverable is a written list of equipment, findings and the records you need to retain. That is how we approach it.
Perspective
Most of the gaps we see in a risk assessment come from the outdoor and underground side of the property. A plan will state that hydrants are inspected, but nobody can say where the private hydrants are, who last operated them or whether the barrel drains in winter.
Our view is that the assessment should start with equipment identification. Once every hydrant, riser, standpipe and backflow assembly is located and recorded, the rest of the document has something solid to stand on, and the maintenance calendar practically writes itself.
The second point is the context. A hydrant at a grain facility, a hotel and a municipal yard may be the same product, but the access, the freezing exposure and the consequences of an outage differ. We assess the site and its operating context before any work is arranged, so that the scope fits the property.
The third is records. A repaired hydrant with no dated entry is, on paper, still a deficiency. We support recordkeeping so that what was done is documented in the form your fire department expects.
Kevin
Getting help for your property
If you need an equipment survey, a hydrant inspection or a maintenance schedule to support your assessment, our hydrant services are the place to start, and the fire protection guide shows the rest of our work, including underground repairs. We work in Grande Prairie, Dawson Creek and the Peace Region, and we offer 24 hour emergency response for locations within 200 km. Contact us to confirm availability for your location.

For more field notes on codes and maintenance, see our blog.
FAQ
Is a fire risk assessment required for every commercial building in Alberta?
The National Fire Code, Alberta Edition, makes the owner or the owner’s agent responsible for compliance, and the City of Edmonton’s checklist is a self-assessment tool for that purpose. A fire safety plan is required for certain occupancies and for buildings with storage, flammable liquid areas or hazardous processes. Confirm what applies to your building with your local fire department.
What is the difference between a fire risk assessment and a fire inspection?
The assessment is the owner’s own review of hazards, people and controls. An inspection is carried out by the authority having jurisdiction. In BC, for example, only a designated fire inspector may conduct a fire safety inspection. A thorough assessment with current records makes an inspection easier to pass.
Who should carry out the assessment?
Someone who knows the building, its occupants and the code. For the fire protection systems, bring in qualified personnel: water-based systems must be maintained to NFPA 25 and the work is generally limited to people acceptable to the local authority. We handle that side for hydrants, sprinklers, standpipes and backflow assemblies.
How long should I keep the records?
It depends on the jurisdiction and the record. Calgary’s guidance asks for the current and previous five years of test and maintenance records, with initial verification reports kept for the life of the system. Ask your local fire department for the rule that applies to you.
Sources
- GOV.UK: Fire safety risk assessment, offices and shops
- GOV.UK: Fire risk assessments
- GOV.UK: Fire safety risk assessment 5-step checklist
- CCOHS: Fire Protection
- City of London: Fire Safety Plan Template
- City of Edmonton: Fire Safety Checklist Booklet for Businesses
- Town of Morinville: Building Owner’s Responsibilities for Fire Safety
- City of Calgary: Fire Safety Maintenance Requirements
- Devon and Somerset Fire and Rescue Service: Five steps to fire risk assessment
- Artémis: Inspection de conformité électrique